# BMC targets early 2027 opening for Byculla Zoo’s ₹62-crore aquarium

**Archive report · 2026-09-20**

The BMC’s planned walk-through aquarium at Byculla Zoo was about halfway complete and being targeted for an early-2027 opening, according to officials quoted on 20 September 2026. The ₹62-crore project remained under construction. The target was an administrative forecast, not confirmation that visitors could already enter the attraction.

## What the September progress account described

The Times of India reported two proposed tunnels, measuring 14 metres and 36 metres, with more than 60 aquatic species envisaged. The aquarium would need life-support infrastructure as well as visitor-facing construction. Municipal commissioner Ashwini Bhide reviewed progress, while the eventual admission charge had not been decided in the cited account.

These details show why a percentage-complete statement needs context. A tunnel’s structure, the equipment maintaining its water and the arrangements for living collections are different components. A progress estimate does not certify that all have been tested together or that a public opening has received its final clearance.

## The aquarium sits within a broader expansion programme

Mumbai Mirror’s 28 February budget account had described ₹136 crore allocated for the zoo’s wider expansion in 2026–27, compared with ₹44 crore in the preceding year. Its coverage included the aquarium and proposals for additional animal habitats. The wider allocation should not be described as the aquarium’s construction price: the two figures have different scopes.

The February report also said Central Zoo Authority approval would be needed before exotic species were introduced under the expansion proposals. That is a condition attached to those plans, rather than evidence that every proposed animal had already arrived. Earlier forecasts about completion and the species collection should likewise remain forecasts instead of becoming a confirmed inventory.

## What remains to be demonstrated before opening

For a publicly funded attraction, completion has both a construction meaning and a service meaning. Residents would need a clear opening notice, access arrangements and admission terms before treating the facility as available. Animal-care and operational readiness matter alongside the finished visitor route.

A useful subsequent administrative account would distinguish the sanctioned project cost, work completed, expenditure incurred and any revised schedule. That would allow readers to assess progress without confusing a budget provision with money already spent or a target month with an enforceable visitor booking date.

The confirmed September development was the reported construction progress and the early-2027 target following civic review. This archive does not certify the aquarium’s readiness, adopt later opening information or promise increased tourism revenue. Byculla Zoo’s public investment is the subject of the report; a projected opening remains conditional until the authority announces and delivers it.

## Quick answers

### Was the aquarium open in September 2026?

No. The cited report described work in progress and an early-2027 target.

### Are ₹62 crore and ₹136 crore the same project figure?

No. The first was the reported aquarium cost; the second concerned the wider zoo expansion allocation.

### Had a new admission price been fixed?

The September account said the fee had not yet been decided.

## Sources and archive context

[The Times of India, 20 September 2026: aquarium progress and opening target](https://timesofindia.indiatimes.com/city/mumbai/walk-through-aquarium-coming-up-at-byculla-zoo-in-mumbai-early-next-year/amp_articleshow/134359795.cms)

[Mumbai Mirror, 28 February 2026: wider zoo expansion budget and approval conditions](https://www.mumbaimirror.com/mumbai/bmc-budgets-%60136cr-for-expansion-of-byculla-zoo-697420)

This report records the position at the stated historical publication date. Proposals, allegations and anticipated events are not presented as final outcomes.

[More Mumbai political news](https://indianvoter.com/category/political-news/cities/mumbai/) · [IndianVoter newsroom](https://indianvoter.com/news/)

## Image source

The Byculla Zoo entrance photographed on 18 May 2008. Archive image of the existing zoo; not the new aquarium or its September 2026 construction progress. Photo: Elroy Serrao / [Wikimedia Commons original file page](https://commons.wikimedia.org/wiki/File:Entrance_byculla_zoo.jpg) · [CC BY-SA 2.0](https://creativecommons.org/licenses/by-sa/2.0). Resized where applicable; display crops may be applied. The photograph remains under the linked licence.